Wombarra Civil Construction
NT Department of Logistics & Infrastructure

Gunn Point Road Shoulder Rehabilitation

Improves road safety for public use and controls corridor erosion.

All Projects
Location
Howard Springs, NT
Duration
May 2026 – June 2026
Value
$500K – $1M
Client
NT Department of Logistics & Infrastructure
Scope of Works
  • 3km of shoulder rehabilitation (Ch 0.0 – Ch 3.0)
  • Clear and grub; neat saw-cut of existing seal
  • Top up with imported Type 2 material; compact shoulders to 98% MMDD
  • Prime and seal to form 8.6m carriageway; re-instate edge line
  • Re-grade batters and install new guideposts